Construction Site Manager with more then 08 years of experience in site supervision. Outstanding projects are done ahead of schedule and under budget. Highly-capable Site Manager with talents in direct project planning and management. Seeking a challenging position in construction field (Construction Management) in a progressive organization, to steer the organization in the right direction by investing all my post qualification and professional expertise, valuable experience to the optimum level, to facilitate mutual growth for both, the organization and personnel career

Overview

9
9
years of professional experience

Work History

Site Project Manager

B. H. LADWA Limited
Dodoma
05.2022 - Current
  • Total Project Cost: USD 1.1 Million.
  • Proposed Construction of National Disaster Management Center. Dodoma
  • to be builte 2500 sqm godown for government notational disaster storage.
  • Interviewed and hired qualified candidates to fill open staff positions.
  • Retained records of supplies and tools used and tasks performed for each project.

Site Project Manager

B. H. LADWA Limited
Kibaigwa ,dodoma
04.2022 - Current
  • Total Project Cost: USD 1.7 Million.
  • Proposed Construction of Post-harvest Centre of Excellence for Grains at Strategic Market Center lot-3. Kibaigwa

Site Project Manager

B. H. LADWA Limited
03.2019 - 02.2022
  • Construction and commissioning of infrastructures projects at the both banks of Rufiji river, Julius Nyerere Hydroelectric Power Plant Project.
  • Total Project Cost: USD 3.8 million
  • Different sizes of housing units.
  • Restaurant, kitchen, stores having capacity for the 500+ employee.
  • Internal RCC roads
  • Worship buildings
  • Sizable gymnasium buildings
  • Performed routine audits to maintain inventories, supplies and equipment.
  • Interpreted blueprints and plans and relayed information to team of workers.
  • Complied with operational standards and OSHA regulations.
  • Club/entertainment centers/buildings
  • underground water tanks, septic tanks.
  • Water supply networks, sewerage system, electricity.
  • Reporting to: the Project Director and the Operation Manager (Head Office, Dar es Salaam)
  • Monitored worksite personnel to maintain high levels of quality and performance.
  • Directed site activities to drive smooth operations and achieve quality assurance metrics.
  • Maintained daily communication with subcontractors and inspectors to drive forward progress of project.
  • Interviewed and hired qualified candidates to fill open staff positions.
  • Maintained safe operating compliance and verified that operations met best practice standards.
  • Retained records of supplies and tools used and tasks performed for each project.
  • Inspected and evaluated physical condition of establishment to comply with safety, quality and service requirements.
  • Employed cost management techniques to maintain budget and increase revenue.
  • Maintained payroll data, attendance records and delivered materials to job site on time and in good condition.
  • Organized and participated in monthly on-site meetings with clientele and subcontractors.
  • Prepared weekly schedules to verify proper floor coverage within fiscal guidelines.
  • Coordinated schedules of vendors and service providers to handle diverse operational and supply needs.
  • Modified plans in response to delays, bad weather or construction site emergencies.
  • Managed and led team of workers in large-scale civil projects.
  • Reduced employee and subcontractor turnover rate.
  • Communicated with local business owners and community members to facilitate use of resources.

Project Site Manager

B.H.ladwa ltd
Negengere.MOROGORO
08.2017 - 02.2019
  • Railway line Staff Quarters for (MOTA ENGIL, Africa) Ngerengere Village,
  • Total Project Cost: USD 1.5 million

Site Manager

Process Plant, Tobacco
02.2017 - 05.2017

Process Plant (Tobacco)

labour contract to built marlboro cigarettes processing plant.

Total Project Cost: USD 100,000.

Site Manager

B.H.ladwa ltd
Morogoro
03.2015 - 10.2016

T M J Hospital cum Residential Complex .Morogoro

- Total Project Cost: USD 400,000.

  • Monitored worksite personnel to maintain high levels of quality and performance.
  • Maintained daily communication with subcontractors and inspectors to drive forward progress of project.
  • Organized and participated in monthly on-site meetings with clientele and subcontractors.

PATEL CONSTRUCTION
07.2014 - 02.2015
  • PATEL CONSTRUCTION
  • elevated waters tank of capacity 50,000liter to supply 30 ruler area village near narama river at rajpipla. vadodara.

Education

Bachelor of Engineering - its civil branch

Karan Sanjaykumar

B. E. CIVIL -

Parul Institute of Engineering & Technology, Gujarat Technological University

Skills

  • Renovations, building and demolition
  • OSHA safety requirements
  • Building site supervision
  • Documentation And Reporting
  • Planning and design
  • Project budgeting
  • Concrete estimation
  • Baseline schedules creation
  • Skilled in Auto cad,MS project,MS office
  • Construction management and administration
  • Permit processing
  • Local rates to cost estimates
  • Project management

Affiliations

PROJECTs:

- Heavy metal contamination on black cotton soil, and

- Study of geotechnical properties of fertilizer contaminated soil.

SEMINARs:

- Wastewater treatment plant,

- Rainwater harvesting, and

- Reinforced Cement Concrete (R. C. C.) Roads.

Industrial Visits

- Housing Complex (Duplex and Apartments) constructions, Vadodara,

- Bridge construction, Vadodara,

- Hydropower generation at KADANA DAM, Gujarat,

- Purification and supplying of water at French well, Vasad,

- Water treatment process plant at NIMETA, Vadodara,

- Sewage treatment process plant, GAJRAWADI, Vadodara,

- Rain Water Harvesting System at Sevatirth, Jamva,

- Bio-Gas Plant at Sevatirth, Jamva, and

- Waste water process treatment plant, G S F C (a large fertilizer manufacturing unit).

Languages

  • 1) English
  • 2) Hindi (India’s National Language)
  • 3) Gujarati (Mother Tongue)
  • 4) swahili (Tanzania National Language)
  • 5) French

Timeline

Site Project Manager

B. H. LADWA Limited
05.2022 - Current

Site Project Manager

B. H. LADWA Limited
04.2022 - Current

Site Project Manager

B. H. LADWA Limited
03.2019 - 02.2022

Project Site Manager

B.H.ladwa ltd
08.2017 - 02.2019

Site Manager

Process Plant, Tobacco
02.2017 - 05.2017

Site Manager

B.H.ladwa ltd
03.2015 - 10.2016

PATEL CONSTRUCTION
07.2014 - 02.2015

Bachelor of Engineering - its civil branch

Karan Sanjaykumar

B. E. CIVIL -

Parul Institute of Engineering & Technology, Gujarat Technological University
Karan Shah